Since decades Blomme is active in the region of Nieuwpoort, Middelkerke, Veurne and Ostend and an established player in building materials and groundworks. On May 5, 1990 the previous concrete plant was solemnly put into operation. This was also a realization of Lybover BULK (Motogroup). 30 years later, Betoncentrale Blomme contacted Lybover BULK again to build a completely new concrete plant.

Big challenge was to limit the production downtime to 6 weeks. After all, the new concrete plant was built on the old foundations. This project consisted of 5 large parts: aggregate storage, underground dosing and weighing unit, feed conveyor, mixing tower and various concrete silos. All essential components were built by our own production workshop in Bruges and Waregem. 